ASHRAE Technical Committee 7.9 - Building Commissioning

RESEARCH

 

Planned Research Activities
Current Research Projects
Completed Research Projects
Non-prioritized Research Ideas
Other Research Documents


Planned Research Activities

The most recent version of the Research Plan prepared for the Research Subcommittee Meeting in Salt Lake City in June 2008. Below is a summary of projects that are currently prioritized by the Research Subcommittee. Priority order not finalized...

Priority
Title
Author
Documents
Most recent status
0
RTAR 1502: User Interface Design for Advanced System Operation
TC 1.4

Jan 09: In the subcommittee meeting, WS 1502 was set as priority #1. RAC conditionally approved this work statement, so it is cycling off our priority list. It is expected to go out for bid shortly.

June 08 report: Project is to be submitted after Salt Lake City for approval in Chicago.

[We were previously referring to this RTAR under the number 1528.]

1
Improved Tools for Control Loop Performance Measurement and Evaluation
Bill Pienta

 

Jan 09 report: Bill distributed new version. He has responded to the issues listed below. Committee continues to support this effort. Put it as priority #2, right after 1502. Might be valuable to have support from another controls vendor, to stress objectivity and non-proprietary nature of the expected results - maybe approach John Seem. Should be submitted with minor changes. The committee voted to ask Bill to make a few minor changes and then submit it to ASHRAE, under the following schedule: deadline for any last minute comments to Bill was January 30th; Bill to send revised version to Dave soon after (received Feb 2nd); Dave to send to those present for final approval, and then submit to ASHRAE for 9 February. The main TC supported this decision. The resulting RTAR (link at left) was submitted 9 February, 2009.

June 08 report: This RTAR has been previously rejected by RAC. The committee gave Bill the following suggestions for improving the RTAR:

  1. The title was changed
  2. Current tools are proprietary, this tool should be available to all.
  3. Research all patents before hand
  4. Create an objective criteria for use on EMCS Systems.
  5. Relate the RTAR more toward commissioning and ongoing commissioning.
2
RTAR 2005-57: Utilization of Random Sampling Technology in Performing Building Commissioning
Kristin Heinemeier

Jay Enck

RTAR

Old RTAR

RAC Comments (gone missing!)

 

Jan 09 report: Jay has the file. Has e-mailed Kristin to request the RAC comments, which Dave did not bring with him.

June 08 report: Jay is willing to carry this RTAR forward with some help from Kristin.

3
WS 1241 - Impact of Commissioning HVAC Systems on Life Cycle Cost
Kristin Heinemeier
RTAR

 

Jan 09: Natascha will keep working on this.

June 08 report: Natascha Castro has agreed to investigate what other research may be ongoing in this area and report back to the subcommittee and to Kristin.

Human Factors in Operations-phase Commissioning
Michael Bobker
June 08: Define and consider the human factors impacts on the acceptance and implementation of findings by building operators from emerging technology represented by tools and platforms for on-going commissioning, FDD, and remote monitoring. Human factors engineering can be applied for improved performance. This research can be seen as an add-on phase to the current generation of research projects and pilots that are developing and testing such tools and platforms. Early findings suggest that there are barriers to resolve on the operations staff side in making full use of the emergent technology. This work would be coordinated with TRG-7's work under the Strategic Plan Objectives.
User Manual for SPC 0
Gerry Kettler
Jan 09: Create a user manual for SPC 0.


Current Research Projects

The Research Subcommittee is represented on the monitoring subcommittee for 1274-RP, which was co-sponsored by this TC.

Title
Sponsoring TC
Contractor
Most recent status
1274-RP: Field Performance Assessment of Packaged Equipment to Quantify the Benefits of Proper Service and Assessing the Long Term Need for Monitoring, FDD, and Continuous Commissioning Technology

7.5, Smart Building Systems

Co-sponsored by TC 7.9

ADM Associates, Inc.

Sponsored by 7.5 (formerly 4.11; Prioritized RTAR.
Jan 08: This project is wrapping up. The contractor has provided a draft final report and also made a final presentation to the PMS.

Jan 09: Todd Rossi is the chair of the PMS. The PMS completely dropped the ball on pushing it to completion. Final report is done and in review. PMS has not provided comments to the contractor yet.

June 08: We received the final report from the contractor and reviewed it at the PMS Meeting yesterday. The committee is to review it and make any changes so that the final documents can be submitted in July. We will post everything from the contractor on the TC website.



Completed Research Projects

The Research Subcommittee co-sponsored project 1032-RP, which is now complete. The Subcommittee also closely followed 1137-RP, which was sponsored by TC 1.4.

Title
Sponsoring TC
Contractor
Most recent status
1137-RP: Field Performance Assessment of VAV Control systems Before and After Commissioning
1.4, Control Theory and Application
Patrick Fleming/ Stantech Consulting
Project is complete. Larry Fisher presented final report at full TC meeting. (June 2004)
1032-RP: Identification and Preservation of Building Design Information for Use in Commissioning and Operations
1.5, Computer Applications
PECI
Reps on PMS: JR Anderson and Eli Howard. Project complete, final report has been delivered, reviewed at last meeting. Symposium will be held in Jan 2003. (June 2002)


Non-prioritized Research Ideas

The Research Subcommittee has identified a large number of research ideas over the past several years. Many of these are described on one-page write-ups or RTARs, and several were developed as work statements. The research ideas that have been written up are summarized in the table below. Other research ideas that have never been written up can be found in the old Research Reports, on the Meetings page.

Title
Author
Documents
Most recent status
Field-Based Evaluation of Methods for Commissioning DDC Systems
Larry Fisher
    Larry Fisher has agreed to write the RTAR and seek TC 1.4 Control Theory and Application as a co-sponsor. (June 2004)
Jan 06 report: Ken will check with Larry and get info to Dave. Larry did not respond, because of international travel.
Jan 07: Ken will ask Larry one more time about this. Possibly the best thing to do would be to take this away from Larry and appoint another champion. That person is Ken Gillespie.
RTAR 2005-56: The Impact of Commissioning on Comfort
Dave Shipley

  June 08 report: The committee as well as the author agree that this RTAR should be dropped.
M&V for Cx
Kristin Heinemeier
    California Commissioning Collaborative is starting a project on this topic, so the Subcommittee decided to drop the topic. (Jan. 2007)
Methods of Improving Persistence of Commissioning Savings in Control Systems
Ken Peet, David Underwood
    Seminar 26 at the January 2007 meeting addressed this topic. This seminar was proposed to find out what is already known and to identify any gaps. Any new topics arising from that seminar can be proposed as a new research topic. The Subcommittee decided to drop this topic, however. (Jan. 2007)
One Time vs Short-Term vs Seasonal Testing of Air-Handling Units
Mingsheng Liu
    This was put on hold until WS-1092, but the original author has been too busy to take further action since then. The Subcommittee decided to drop the topic. (Jan. 2007)
WS 1312 - Tools for Evaluating Fault Detection and Diagnostic Methods for Air-Handling Units
John House
This draft work statement was presented to the Subcommittee at Anaheim. Members had some questions about it, which were not fully resolved during the discussion. The Subcommittee expressed interest in the work statement, and planned to consider it again at the meeting in Nashville. (Jan. 2004)
WS 1115 - Identification of Ideal Monitoring Data Points for Comnmissioning Support During HVAC Design
Dave Shipley
Submitted, accepted, and contractor selected before Tech Council turned it back. We believe some parts may be done by others, so we will reassess need for project, and rescope/redraft WS if necessary. Dave will follow up with Ken Gillespie (PG&E), PECI, and TC1.7 (GPC 4) and make recommendation at next meeting whether to resubmit or drop. (January 2002 - Decision was made in June 2002 to drop this work statement and monitor parallel work by CEC PIER program.)
Quantifying Building Energy Performance Persistence of Savings after Retro-Commissioning
Needs champion
RTAR was rejected with comments. Author revised RTAR. However, much of this work has been done….need to revise to focus on any gaps. (June 2002)
Development and Implementation of Commissioning Strategies for Optimal Control Evaluation
Dave Shipley
Deleted after June 2002 meeting, due to lack of action/interest from TC 4.6. (June 2002)
The Building Automation System's Role in Commissioning of HVAC Systems
Jim Gartner
Deleted after June 2002 meeting due to lack of action/interest from TC 1.4 or from IEA Annex 40 participants. (June 2002)
Diagnostic tools for maintenance, operating and commissioning cost optimization
Tom Tamblyn
No further action was taken on this research idea, due to lack of action/interest from TC 1.8. (Feb 2000)


Other Research Documents

Research Plans: Previous versions of our Research Plans may be found in the meetings area of this site.

Research Meeting Notes: Notes on previous Research Subcommittee meetings may be found in the meetings area of this site.

Sample Size Calculator: In the development of one of our work statements, the Research Subcommittee needed to calculate the sample size required to obtain statistically significant results. We developed a simple spreadsheet for making this calculation, based on the answers to several questions. We are providing the spreadsheet without restriction. Remember, it's usually best to have someone with a good understanding of statistics take a look at your experimental design, so you don't waste time and money collecting data that don't successfully answer the research questions.

Additional Research Ideas: In February 2000, Kenneth Gillespie, of PG&E (contact information on members-only TC website) submitted a list of 27 additional research ideas, with information on their status at that time.

Subcommittee Membership: A list of Research Subcommittee members is provided. TC members can go to the members-only area of the site to obtain contact information for the subcommittee members.

Other Documents: Some additional documents are not currently being provided on the public area of the site. TC members can go to the members-only area of the site to review them.

All files are in Adobe Acrobat format. The Adobe Acrobat Reader may be downloaded free from the Adobe web site. To download files using Internet Explorer, Right-click the document name and choose "Save Target As" option.

Research Chair:

Dave Shipley
Marbek Resource Consultants
eMail: Dave Shipley (shipley@marbek.ca)